a critical path for a project is the series of activites that determine the earliest time by which the project can be completed.

Emphasis on "earliest time".

In a trial exam my students did some put that the "critical path is the longest path which a project cannot be delayed wthout delaying the entire project"

Emphasis on "longest time". Would this answer be accesptable in an exam?
Is it "earliest time" or "longest path" or both is ok. 

Thank you for any replies.  

Paul Golub
Santa Maria College
50 Separation Street
Northcote 3070
Ph: 9488 1674
_____________________________________________________________________________
 This email and any attachments may be confidential.  You must not disclose 
 or use the information in this email if you are not the intended recipient.
 If you have received this email in error, please notify us immediately and 
 delete the email and all copies.  The College does not guarantee that this  
 email is virus or error free.  The attached files are provided and may only
 be used on the basis that the user assumes all responsibility for any loss,
 damage or consequence resulting directly or indirectly from the use of the 
 attached files, whether caused by the negligence of the sender or not.  The
 content and opinions in this email are not necessarily those of the College
____________________________________________________________________________



More information about the itapps mailing list