[Year 12 IT Apps] information needed for gantt charts
Timmer-Arends
timmer at melbpc.org.au
Fri Mar 6 20:02:03 EST 2009
Sorry about this, but the teacher in me couldn't let the quotes I wrote
about this earlier go without translating it into something students could
digest, and here is what it came up with:
Lead and Lag times are both enforced delays; that is, there is something in
the nature of a task that forces a delay that the project planner must take
into account.
The distinction is this:
If task B is dependent on task A and B cannot begin immediately after the
completion of A, then the delay is called:
a Lead if it is caused by B
a Lag if it is caused by A
In contrast, Slack and Float are both artifacts of the project planning
process:
If task B is dependent on A and we are unsure of how long A will take, then
we may choose to schedule B at a later start time so as to allow for a later
than expected completion of A. In other words, we build some Slack into task
A.
While Float occurs between parallel sequences feeding into a common
dependency:
If C is dependent on both A and B, but A and B can be run in parallel, then
the Float is the difference in time between A and B (the path on which there
is no float is the critical path).
Pictures would be very useful at this point.
Regards
Robert T-A
Brighton SC
----- Original Message -----
From: "Mark Kelly" <kel at mckinnonsc.vic.edu.au>
To: "Year 12 IT Applications Teachers' Mailing List"
<itapps at edulists.com.au>
Sent: Friday, March 06, 2009 8:23 AM
Subject: Re: [Year 12 IT Apps] information needed for gantt charts
I've always read that slack = float.
Timmer-Arends wrote:
> Since everybody else is having a go....
> "A lead is a forced wait before a task can commence; eg scheduling a Post
> Implementation Review on a project for two weeks after the installation
> date. There may be no intervening activity planned, but we have to wait
> anyway"
> "A lag is a forced wait after an activity before an event can occur; eg
> you might throw a concrete floor and then have to wait three days for it
> to cure before laying it with tiles"
> "the slack time for an event is given by subtracting its earliest time
> from its latest time. This is a measure of the delay which the event could
> suffer ...and still allow the project to finish within the original
> estimate range"
> "The float time is the amount of time that a task start could be delayed
> without affecting the date upon which the succeeding event would occur
> "Managing Information Technology Projects", McLeod and Smith (University
> of Cape Town), Course Technology, 1996
> ...and then there is the question of how deeply does one have to go into
> all of this anyway?
> Regards
> Robert T-A
> Brighton SC
> ----- Original Message -----
>
> *From:* PARAGREEN, Chris <mailto:Chris.PARAGREEN at kew.vic.edu.au>
> *To:* Year 12 IT Applications Teachers' Mailing List
> <mailto:itapps at edulists.com.au>
> *Sent:* Thursday, March 05, 2009 12:36 PM
> *Subject:* RE: [Year 12 IT Apps] information needed for gantt charts
>
> My first post as a newbie IT teacher!
>
>
> “Just” a question about some of the definitions for Gantt charts….
>
> According to Potts (p30), lead time is, “… time leading up to or
> before a task.” It further explains the concept, but essentially
> this is it.
>
> My understanding is that lead time is the time available to begin a
> dependant task before its predecessor is finished.
>
> For example, you can’t set up a computer until the box has arrived,
> but you can prepare the room in advance.
>
>
> Similarly, Potts states that slack time and lag time are the same
> thing, whereas I think they are not.
>
> Slack is the available time to allow for delays, but lag is the time
> between when a task finishes and when it’s dependant task can begin.
>
> For example, if pouring concrete, the actually pouring task might
> have finished, but you have to wait for the concrete to cure (the
> lag time) before you can paint it.
>
>
> Are my definitions too precise for what we need to teach, am I
> wrong, or am I missing something?
>
>
> Regards,
>
>
>
> Chris Paragreen
>
--
Mark Kelly
Manager - Information Systems
McKinnon Secondary College
McKinnon Rd McKinnon 3204, Victoria, Australia
Direct line / Voicemail: 8520 9085
School Phone +613 8520 9000
School Fax +613 9578 9253
kel at mckinnonsc.vic.edu.au
Webmaster - http://www.mckinnonsc.vic.edu.au
IT Lecture notes: http://vceit.com
Moderator: IT Applications Mailing List
RealMenDon'tNeedSpacebars.
_______________________________________________
http://www.edulists.com.au - FAQ, resources, subscribe, unsubscribe
IT Applications Mailing List kindly supported by
http://www.vcaa.vic.edu.au/vce/studies/infotech/itapplications3-4.html -
Victorian Curriculum and Assessment Authority and
http://www.vitta.org.au - VITTA Victorian Information Technology Teachers
Association Inc
More information about the itapps
mailing list