[Year 12 IT Apps] information needed for gantt charts
Mark Scott
msc at luther.vic.edu.au
Thu Mar 5 14:03:51 EST 2009
Gotta love good old wikipedia.
The definitive source of info for students
Mark Scott
-----Original Message-----
From: itapps-bounces at edulists.com.au [mailto:itapps-bounces at edulists.com.au] On Behalf Of Mark Kelly
Sent: Thursday, 5 March 2009 1:52 PM
To: Year 12 IT Applications Teachers' Mailing List
Subject: Re: [Year 12 IT Apps] information needed for gantt charts
Hmmm. I have trouble with that first definition by Wikipedia. I've
never heard of lead time defined like that before.
Mark Scott wrote:
>
> In Project Management Lead Time is the time it takes to complete a task
> or a set of interdependent tasks. The Lead Time of the entire project
> would be the overall duration of the critical path for the project.
>
> http://en.wikipedia.org/wiki/Lead_time#Lead_time_in_Project_Management
>
>
> The time required by one task before another task can begin.
>
> Baker, S & K. Baker. On Time/On Budget, Prentice Hall, Englewood Cliffs,
> NJ, 1992
>
>
> An overlap between tasks that have a dependency.
>
> Glossary, User's Guide for Microsoft Project 98, Microsoft Corporation,
> 1997, p307
>
>
> A technique called */lead time/* is used to represent partial
> dependencies. By using lead time, certain tasks can overlap by a fixed
> amount or by a percentage of the predecessor task. For example, testing
> can start when 30% of coding is finished. It can be thought of as the
> predecessor task getting a head start, or lead, before the successor
> task starts. Because the term is easy to confuse with Lag Time, lead
> time is also referred to as Overlap or Negative Lag.
>
> http://www.leadingproject.com/wiki/Glossary/LeadTime
>
>
> Occurs when a task should theoretically wait for its predecessor to
> finish, but can actually start a little early. The time that the tasks
> overlap is lead time. For example, when replacing computers in a
> computer lab, you could actually start bringing in the new computers
> while the old ones were being packed up and moved out. The time during
> which packing and unpacking can happen at the same time is /lead time/.
>
> Gospel according to Mark
> <http://www.mckinnonsc.vic.edu.au/vceit/ganttpert/projmanterms.htm> (Kelly)
>
>
> Seems to me that the partial dependency theory definition wins the day
> for Lead time.
>
> Slack and Lag time would seem to be interchangeable for the purposes of
> Units 3 and 4 ITA.
>
> Mark Scott
> Luther College
>
>
> ------------------------------------------------------------------------
> *From:* itapps-bounces at edulists.com.au
> [mailto:itapps-bounces at edulists.com.au] *On Behalf Of *PARAGREEN, Chris
> *Sent:* Thursday, 5 March 2009 12:37 PM
> *To:* Year 12 IT Applications Teachers' Mailing List
> *Subject:* RE: [Year 12 IT Apps] information needed for gantt charts
>
> My first post as a newbie IT teacher!
>
>
>
> "Just" a question about some of the definitions for Gantt charts....
>
> According to Potts (p30), lead time is, "... time leading up to or before
> a task." It further explains the concept, but essentially this is it.
>
> My understanding is that lead time is the time available to begin a
> dependant task before its predecessor is finished.
>
> For example, you can't set up a computer until the box has arrived, but
> you can prepare the room in advance.
>
>
>
> Similarly, Potts states that slack time and lag time are the same thing,
> whereas I think they are not.
>
> Slack is the available time to allow for delays, but lag is the time
> between when a task finishes and when it's dependant task can begin.
>
> For example, if pouring concrete, the actually pouring task might have
> finished, but you have to wait for the concrete to cure (the lag time)
> before you can paint it.
>
>
>
> Are my definitions too precise for what we need to teach, am I wrong, or
> am I missing something?
>
>
>
> Regards,
>
>
>
>
>
> Chris Paragreen
>
> IT, Mathematics and Japanese Teacher and Timetabler
>
> Kew High School
>
> 1393 Burke Road
>
> Kew East VIC 3102
>
> phone +613 9859 8652 fax +613 9819 7880
>
> chris.paragreen at kew.vic.edu.au <mailto:chris.paragreen at kew.vic.edu.au>
>
> *2008 International Year of Languages *
>
> *Languages Still Matter! *
>
--
Mark Kelly
Manager - Information Systems
McKinnon Secondary College
McKinnon Rd McKinnon 3204, Victoria, Australia
Direct line / Voicemail: 8520 9085
School Phone +613 8520 9000
School Fax +613 9578 9253
kel at mckinnonsc.vic.edu.au
Webmaster - http://www.mckinnonsc.vic.edu.au
IT Lecture notes: http://vceit.com
Moderator: IT Applications Mailing List
RealMenDon'tNeedSpacebars.
_______________________________________________
http://www.edulists.com.au - FAQ, resources, subscribe, unsubscribe
IT Applications Mailing List kindly supported by
http://www.vcaa.vic.edu.au/vce/studies/infotech/itapplications3-4.html - Victorian Curriculum and Assessment Authority and
http://www.vitta.org.au - VITTA Victorian Information Technology Teachers Association Inc
More information about the itapps
mailing list